Sunday, June 5, 2016
Saturday, November 8, 2014
Introducing our new home
Finally we packed everything from 24 Heritage Dr and moving to our new home, 35 Blue Spruce.
Here is quick peek of new home -
Here is quick peek of new home -
Friday, November 7, 2014
Monday, October 27, 2014
Almost there
We are closing on Nov 7th which is less than 2 weeks now. Final walk through will be on 3rd November.
Allmost all the things are in place now, lights, cabinets, counter tops, wall colors, bathroom fixtures on and on and on....
Allmost all the things are in place now, lights, cabinets, counter tops, wall colors, bathroom fixtures on and on and on....
![]() |
| Fresh green lawn is growing. Letter box is also placed. |
![]() |
| Front door stained. |
![]() |
| Foyer Chandelier |
![]() |
| Lights on columns. |
![]() |
| Cabinets in family room |
![]() |
| Chandelier in dinning room |
![]() |
| First floor bath vanity |
![]() |
| Master bathroom |
![]() |
| Master bathroom |
![]() |
| Night shot |
Tuesday, October 21, 2014
Wednesday, October 8, 2014
Tuesday, September 16, 2014
Saturday, September 13, 2014
Friday, September 12, 2014
Internals in progress
Today we visited to so see so many surprises.
Stairs and railing work is completed. Now we need to decide on stain colors.
Special order bath tub in Ram and Jai's shared bathroom is installed. Next addition would be shower doors.
Fireplace mantle and hearth is placed.
Deck is finally ready
Most of all wood planks are delivered to be installed next week
It is fun to see everything being installed and house is getting ready using our selections.
Stairs and railing work is completed. Now we need to decide on stain colors.
Special order bath tub in Ram and Jai's shared bathroom is installed. Next addition would be shower doors.
Fireplace mantle and hearth is placed.
Deck is finally ready
Most of all wood planks are delivered to be installed next week
It is fun to see everything being installed and house is getting ready using our selections.
Wednesday, September 3, 2014
Lighting Fixtures selection done
It took 3 visits to finalize light fixtures. Finally all work done. We did great job here. Thanks to Frank from Connecticut Lighting.
Friday, August 22, 2014
Internals - Insulation started
Today we visited Rob for bunch of items for clarifications and selection confirmations.
Baba wanted to visit site during their work time to see how they work. He was curious about how they put insulation.
It looks like they have finished most of the exterior items, excluding those small roof portions.
Baba wanted to visit site during their work time to see how they work. He was curious about how they put insulation.
![]() |
| Stock of insulation |
![]() |
| Looks almost complete |
Wednesday, August 20, 2014
Bricks and siding finished - Exterior is almost done
Today we visited the house, it is fascinating to see it getting built as we had imagined on paper before few months.
Brick work on front side is finished. They have almost finished sidings work on rest of the three sides. All the windows are in place now.
Lots of things are going on inside. Both fireplaces are installed, electrical wiring is going on, plumbing and bathroom works are going on. Central vacuum system is also getting installed.
![]() |
| Our selection: Colonial White |
![]() |
| Our selection: Colonial Red |
Selections are going on for counter tops (granite and cultured marble), we have appointment tomorrow for lighting fixtures.
We were told that, we will get a beautiful sunset. Indeed....
![]() |
| Beautiful capture by Baba |
Thursday, August 14, 2014
Subscribe to: